12th St, Pine to Fairbanks
College Ave, 14th to Graves Place
Schedule
·
Construction
begins May
2008
·
Construction
substantially completed Thanksgiving
2008
Specifications
·
12th St, Pine to
College: Water main, sanitary sewer and
roadway replacement. Storm sewer will be
replaced as necessary. The recently replaced
Pine and River intersections will not be disturbed.
·
12th St, College
to Columbia: Water main and sanitary sewer
replacement.
·
12th St,
Columbia to Lincoln: Water main and
sanitary sewer replacement. Restoration
will reflect the planned vacation of this portion of 12th St.
·
12th St, Lincoln
to Fairbanks: Water main and sanitary
sewer replacement. The roadway will be
resurfaced as necessary.
·
College, 14th to
Graves Place: Water main
replacement. Roadway and storm sewer
will be replace between 12th St and Graves Pl.
·
12th St Construction Plan
Set.pdf
Funding
·
This project
will be funded by the Holland BPW and the City of Holland with no anticipated
out-of-pocket costs for customers and residents.
Additional Information
·
Customers will
receive 24 hours notice prior to interruptions in water service.
·
Sewer service
interruptions are not anticipated.
·
Access will be
maintained for customers located within the project limits. However, driveway access may be impacted for
short periods of time as part of typical construction activities. Additional driveway access restrictions may
be necessary when pavement is being placed.
·
Sprinklers
and/or landscaping located within the affected rights-of-way are subject to the
City’s Lawn Component Policy located herein.
·
Affected
customers will receive additional information in the form of mailings and
meetings as plans and schedules are developed.
One of the mailings will include contact information for Holland BPW,
City of Holland and Contractor personnel for use in the event of questions or
concerns.
·
March
25, 2008 Open House Invitation.pdf
·
May
15, 2008 Open House Invitation.pdf
·
Please visit
this site regularly for updates.
Contacts
On-Site
Inspector John
Walsh 616.723.3914
Water
& Sanitary Concerns John
Schroeder 616.218.9965
Road
& Drainage Concerns Ben 616.928.2427
Wyoming
Excavators Nate 616.691.7368
x 12
After-Hours
Concerns Paul 616.293.3926
Life
of Property Threatening Emergencies 911
Country Club Rd, Euna Vista to 16th
Schedule
·
Construction
begins May
12, 2008
·
Construction
substantially completed September
30, 2008
Specifications
·
Country Club Rd,
8th to 16th: Water
main, storm sewer and roadway replacement and curb & gutter, sidewalk and
sanitary sewer installation.
·
Country Club Rd,
Euna Vista to 8th: Storm
sewer installation and roadway replacement.
·
Country Club Rd Construction Plan
Set.pdf
Funding
·
This project
will be funded by the Holland BPW and the City of Holland. Affected customers and residents will be
assessed for curb & gutter, sidewalk and sanitary sewer.
Additional Information
·
Customers will
receive 24 hours notice prior to interruptions in water service.
·
Sewer service
interruptions are not anticipated.
·
Country Club Rd
from 8th to 16th will be closed to all through traffic
during the project. However, local
traffic will be maintained for customers and residents living within the project
limits. Driveway access may be impacted
for short periods of time as part of typical construction activities. Additional driveway access restrictions may
be necessary when pavement is being placed.
During these times you will be allowed to part overnight on side steets
without being cited. The Holland Police
Department will be informed not to cite vehicles registered to Country Club Rd
addresses.
·
Sprinklers
and/or landscaping located within the affected rights-of-way are subject to the
City’s Lawn Component Policy located herein.
·
Please visit
this site regularly for updates.
Contacts
On-Site
Inspector Gene 616.396.0255
Water
& Sanitary Concerns Doug 616.836.3712
Road
& Drainage Concerns Ben 616.928.2427
Triangle
Excavators Steve 616.355.7787
After-Hours
Concerns Steve 616.836.1942
After-Hours
Concerns Mike 616.836.7194
Life
of Property Threatening Emergencies 911
40th St, Washington to College
Schedule
·
Construction Spring
/ Summer 2009
Contacts
General
Project Information Adam 616.355.1564