Street Reconstruction Projects

The Holland BPW is partnering with the City of Holland to reconstruct the water, wastewater & storm systems and roadway in the below referenced locations.  Construction is anticipated to begin in the Spring of 2010 with completion scheduled for the Fall of 2010.  Engineering is being performed by OMM Engineering, Inc of Grand Rapids, MI.

40th Street, Washington to Lincoln

Construction began Monday, March 29, 2010 with the removal of pavement between College & Lincoln.  Utilities are being replaced now.  This project will progress from east to west.

Proposed Construction Map showing Phases
 Construction Drawings

Project Information -
Total road reconstruction to update underground utilities, upgrade storm sewer line, add curb & gutter and then repave the roadway.

Update -
The first phase between Lincoln to College is complete. Final layer of asphalt will go down on the entire project at once at the end in August/September.  The contractor has moved to the 2nd phase between College and Pine for utility replacements.

Phases -
Construction will be done in Three Phases to minimize disruption to 40th St. residents.  All dates are weather depending.

  • Phase   I - 40th St from Lincoln to just east of College Avenue.
    Road will be closed to through traffic May 29 - May 7. COMPLETE
  • Phase  II - 40th St from just east of College to just east of Pine Avenue.
    Road will be closed to through traffic May 10 - July 2.
  • Phase III - 40th St from just east of Pine to Washington Avenues.
    Road will be closed to through traffic from July 5 - August 27.

Paving – Final paving from Lincoln to Washington will be complete Approx. Sept. 15

Contact Information -
On-Site Representative & After Hours    Doug      616.292.4836
Concerns


Roadway, Storm Water, Sidewalk,
Footing/Dump Drain, Tree Concerns      Ben        616.928.2400

Water/Wastewater Concerns                 Adam      616.355.1564

Life/Property Threatening Emergencies                 911

18th Street, Cleveland to River & Harrison Ave, 18th to 19th

Proposed Construction Map showing Potential Phases
Construction Drawings

Update -
Work began on Phase 1 on May 17, 2010 with pavement removal.  Utility replacement will follow starting in Cleveland between 17th and 18th Streets and will proceed eastward down 18th Street to Van Raalte.

Construction will proceed in three phases from west to east to minimize disruption to 18th Street residents.  All dates are weather depending.

  • Phase   I - 18th from Cleveland to Van Raalte Ave, and Cleveland from 17th to 18th St.
    Closed to through traffic from May 14 to June 26
  • Phase  II - 18th from Van Raalte to Maple Ave and Washington Ave from 17th - 18th St.
    Closed to through traffic from June 28 to July 31.  Closure will include the intersection of VanRaalte Ave at 18th Street.
  • Phase III - 18th from Maple to River Ave.
    Closed to through traffic from August 2 to September 3.

Notice sent to residents 5/11/2010 regarding start of construction and backwater valves
Notice sent to residents 12/11/2009
Lawn Component Policy

Contact Information -
On-Site Representative                            Kelly       616.322.2392
Contractor: Wyoming Excavators            Nate       616.691.7368, Ext 12
24-Hour Contractor Contacts                   Paul        616.293.3926
                                                                     Nate       616.293.3924
                                                                     Chuck     616.293.3927
Roadway, Storm Water, Sidewalk,
Footing/Dump Drain, Tree Concerns      Ben        616.928.2400
Water/Wastewater Concerns                   Joe         616.355.1643
Life/Property Threatening Emergencies                 911

Para recibir esta informacion en espanol, llame al (616) 355-1500 de lunes a viernes, de 8:00 AM a 4:00 PM.

Upcoming Projects in 2010

Sunset & Sunrise Water Main Replacement.  Replacement of all water mains north of 8th Street via a trenchless technology known as Horizontal Directional Drilling.  Holes will be dug for each individual home's reconnection to the new water main.  Plans are currently under development.

Sanitary Sewer Main Lining - Insertion of a cured-in-place liner inside select sanitary sewer mains throughout the Holland BPW sewer service area.  This is a trenchless technology to rehabilitate old sanitary sewers without the costly excavation and lengthy disruption to public services.

___________________________________________________________________________

Please visit the Holland City’s Website for information regarding these projects:

48th Street: City Limits to Matt Urban & Matt Urban Drive: 48th to Washington